Bridge move planned for next Monday.

BATH NEWSEUM

As part of the regeneration of Bath Riverside, the Destructor Bridge is being replaced with a new bridge designed to accommodate cycles, pedestrians, buses and vehicles for Bath Riverside residents. Some local amenities are affected by these works which commenced in April 2015. 

P1000031

During the initial launch in late April, the bridge started to move slightly off its required very precise alignment and the contractor, Britannia Construction, has now put in place measures to prevent this happening. 

Britannia Construction now aim to move the new bridge into place between Monday 18th July and Wednesday 20th July 2016 (inclusive). This work will necessitate the temporary closure of the river and towpath as well as Bath and North East Somerset Council’s Recycling Centre on Upper Bristol Road.

P1000035 So close and yet so far.

River Avon Towpath

During the works to replace Bath’s Destructor Bridge, the National Cycle Network (NCN4 route)…

View original post 268 more words

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s